5S Implementation in Kelachandra Pipe Industries and Fittings Kerala

July 31, 2017

Project Brief: Lean Manufacturing at Kelachandra Pipe Industries and fittings. Project Details: Before the engagement, the setup time of PVC machines was more than 3 hours, we reduced the setup times of the pipe extrusion machine to 23 minutes. Similarly

Read More Download Case Study

5S Implementation at Falcon Agencies, Calicut and Kochi

July 31, 2017

Project Brief: 5S implementation at Falcon Agencies, Calicut and Kochi. Falcon Agencies is a part of Paragon and they are distributing Paragon Footwear to Kerala wholesalers and Retailers. Their warehouse is more than 20000 sq.ft. Project Details: Lot of old/obsolete

Read More Download Case Study